|
Free FrontPage template by wet-inc
|
|
|
|
Allegany County to Upgrade Georges Creek Wastewater Treatment Plant
Allegany County Government is undertaking an important, far-reaching project to improve the Georges Creek Wastewater Treatment Plant (GCWWTP, 25018 Old Reynolds Road, Westernport, MD). The Department of Public Works led by Director W. Stephen Young and Deputy Director Paul F. Kahl and its Utilities Division, managed by Mark W. Yoder, are spearheading this important project. All are Professional Engineers.
MARYLAND DEPARTMENT OF THE ENVIRONMENT
The Maryland Department of the Environment (MDE) has required Allegany County Government to correct deficiencies in the Georges Creek Wastewater Treatment Plant. Specifically, Allegany County entered into a Consent Order with the Maryland Department of the Environment to correct the permit violations and to upgrade the plant. MDE also enacted more restrictive treatment requirements to remove nitrogen and phosphorus from the wastewater: Biological Nutrient Removal (BNR) and Enhanced Nutrient Removal (ENR).
This plant and the associated collection system were constructed in the 1980’s. Over the years, technology has improved and regulations have increased. In recent years the plant has experienced high flows from inflow/infiltration. Overall, the plant’s performance is now poor.
COMPLEX ENGINEERING PROJECT
The Allegany County Department of Public Works and Stearns and Wheler, an engineering firm from Bowie, Maryland, began the design process for the plant upgrade in 2004. The project is complex and the design process was challenging. Since that time, different treatment alternatives were evaluated, associated bid documents were developed, and funding options were reviewed with MDE on numerous occasions.
FUNDING SOURCES
The funding, like the project itself, is complicated. The total project will cost $28.4M. The low construction bid was $24.4M. In addition to construction costs, there are engineering, legal, and administrative costs. The State of Maryland is paying for over two-thirds of the total cost; specifically, the State is providing $19.4M (68%) of the $28.4M.
The funding sources of the Georges Creek Wastewater Treatment Plant upgrade are:
LOCAL USERS
ALTERNATIVE RE-EVALUATED
After the nearly $25 million dollar construction bid was received for the Georges Creek Wastewater Treatment Plant, Allegany County reevaluated the option of pumping flow to another plant, Upper Potomac River Commission (UPRC), near Westernport.
The Allegany County Commissioners and the Allegany County Department of Public Works staff had multiple discussions with representatives from the Maryland Department of the Environment, the Upper Potomac River Commission, and Stearns & Wheler about this alternative. After this review, the Department of Public Works staff advised and the Allegany County Commissioners agreed to proceed with the Georges Creek Wastewater Treatment Plant upgrade.
MINIMAL-NO SAVINGS AND SIGNIFICANT RISK
The UPRC alternative offered minimal or no savings to local users; the local users would pay the same ad valorem for both alternatives. The amount of the project to be funded by loans to Allegany County and paid by local users was similar for both alternatives. The UPRC alternative had a lower total project cost but significantly lower grants as well. Therefore, the cost to local users was nearly equal.
The UPRC alternative had significant risk. The UPRC plant was not designed for either BNR or ENR; although some nitrogen and phosphorus removal would be achieved under the UPRC alternative, the project, once completed, could fail to meet Maryland Department of the Environment’s BNR-ENR requirements.
CONTRACT AND TIMEFRAME
Allegany County Government had a competitive bidding process and awarded the contract to Galway Bay Corporation, Mount Braddock, PA. The Georges Creek Wastewater Treatment Plant upgrade construction will begin this spring and is expected to take two years. ------------------------------------------------------------------------------------------------------------ NOTE: Forbes Media, www.investopedia.com, presents information on ad valorem, click to dictionary on the homepage.
|
|
Copyright 2007 © Allegany County Government, All rights reserved |